| Scope of works for Construction manager position
1. Analysing
- Define and update plan as required for work package priorities
- Ensure tender documents are consistent with site regulations
- Establish management summary for all packages with the discipline leaders and consultants.
- Prepare advance planning for interface actions
2. Organising
- Study complexity, technical & utility implications of each package & prepare plans
- Comment on constructability, installation
- Propose & implement construction techniques & method statements
- Identify interface risks between packages and put in place actions as required.
- Due regard for interfaces, tie ins, subsequent access maintenance
- Supervise all construction & installation of packages & ancillaries
- Exercise Contract prerogatives
- Subcontractor construction progress review
- Coordination of inspection & testing
3. Planning/Scheduling
- Propose recovery strategy to contractors and installers if agreed schedules are not met or at risk.
- Drive the procurement schedule for the work packages with the discipline leaders
- Establish with site supervisor and CM scheduler a 3 week rolling schedule and update.
- Prepare advance planning for interface actions get coordination reports from discipline leaders and ensure with discipline leaders that coordination due diligence exercises are completed.
-
Feed back to scheduler to get updated Detailed Construction Schedules.
4. Supervising
- Supervise all construction and installation, in particular direct supervision of subcontractors and on site vendors
- Develop with CM scheduler Detailed Construction Schedules for work packages
- Schedule, chair, minute meetings, follow up actions there from
- Closely manage interfaces & integration with existing Production Operations & facilities
- Work closely with Project Management to achieve Project objectives
- Inspect all parts of Construction Site monthly
- Prepare detailed punch lists of deficiencies, & manages corrections
- Issues Certificate of (substantial) completion
- Prepare handover report for project phase, recommends Final payments
- Receive manuals warranties guarantees
- Receive as built manuals and drawings
- Phase completion recommended OK for next, & OK for local authorities
5. Safety
- Working with EHS supervisor ensure site safety strategy is respected and applied
- Exercise Contract prerogatives.
- Apply and enforce site safety regulations on site.
6. Reporting
- Prepare weekly reports for issue to project management
- Operatives on site from each contractor
- Weekly targets and milestones achieved
- 3 week look ahead
- Liaise with Logistics manager for weekly report for work packages
- interface reports
- Owned value progress
- organize & manage receptions with contractors
Chemgineering bietet Ihnen in einem dynamischen, zukunftsorientierten Umfeld mit flacher Organisationsstruktur eine vielfältige, herausfordernde Tätigkeit mit attraktiver Vergütung und der administrativen und fachlichen Leitung einer Abteilung.
Nehmen Sie einfach per Mail oder telefonisch Kontakt mit uns auf. Wir garantieren absolute Diskretion.
Chemgineering Technology AG, Güterstrasse 107, 4133 Pratteln 1, Schweiz
Tel. +41-61-467 54 54, Markus Meier, E-Mail:
 |